Question 1020 of 153 · Oklahoma Fire Alarm Technician Exam

After repairing deficiencies found at an annual inspection and applying a green deficiency repair tag, when must the repair document go to the AHJ?

Exactly one answer is correct.

Show solution

Correct answer to question 1020

  • B: Within 5 days of the repairs

Explanation

Within five days of completing the inspection deficiency repairs, a copy of the repair document is provided to the authority having jurisdiction.