Question 6009 of 153 · Oklahoma Fire Alarm Technician Exam

On a construction site, what protection does OSHA require for 120 V, 15 and 20 A temporary receptacles used by workers?

Exactly one answer is correct.

Show solution

Correct answer to question 6009

  • B: Ground fault circuit interrupters or an assured equipment grounding program

Explanation

Temporary 120 V receptacles that are not part of the permanent wiring need GFCI protection, or the employer runs an assured equipment grounding conductor program.

Next to question ›