Question 4044 of 297 · NICET Fire Alarm Systems Level III
The owner's representative asks your technician on site to add four strobes in a new room. What should the Level III project manager require before the work proceeds?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4044
- C: A written change authorization through the contract's change process
Explanation
Added scope should be authorized in writing through the contract's change process, such as a Change Order or Construction Change Directive, before work starts. Otherwise payment and design review of the change are at risk.
More questions: Management and Supervision
- 4045A subcontract requires the fire alarm contractor to carry insurance naming the general contractor as additional insured. What should the project manager provide before starting work?
- 4001Under OSHA construction rules, at what height must workers on a walking-working surface with an unprotected edge generally be protected from falls?
- 4002A technician uses a portable extension ladder to reach a roof edge. How far must the side rails extend above the upper landing?
- 4003A non-self-supporting ladder is 20 ft long to the support point. About how far from the wall should its base be?
- 4004Your crew must work on a 120 V circuit that feeds the fire alarm control unit. What does OSHA require before work begins on it?
- 4005On a construction site, what does OSHA require for 120 V, 15 and 20 A temporary receptacles used by your crew?