The owner's representative asks your technician on site to add four strobes in a new room. What should the Level III project manager require before the work proceeds?

Exactly one answer is correct.

Show solution

Correct answer to question 4044

  • C: A written change authorization through the contract's change process

Explanation

Added scope should be authorized in writing through the contract's change process, such as a Change Order or Construction Change Directive, before work starts. Otherwise payment and design review of the change are at risk.