- 4001Under OSHA construction rules, at what height must workers on a walking-working surface with an unprotected edge generally be protected from falls?
- 4002A technician uses a portable extension ladder to reach a roof edge. How far must the side rails extend above the upper landing?
- 4003A non-self-supporting ladder is 20 ft long to the support point. About how far from the wall should its base be?
- 4004Your crew must work on a 120 V circuit that feeds the fire alarm control unit. What does OSHA require before work begins on it?
- 4005On a construction site, what does OSHA require for 120 V, 15 and 20 A temporary receptacles used by your crew?
- 4006A technician works from the platform of a boom-supported aerial lift. What fall protection is required?
- 4007Your crew drills many holes in concrete for device mounting. Which OSHA standard addresses the dust hazard?
- 4008How long must an employer keep OSHA 300 logs of work injuries and illnesses?
- 4009A worker is killed on a jobsite. Within how many hours must the employer report it to OSHA?
- 4010A worker suffers an amputation of a fingertip on site. Within how many hours must the employer report it to OSHA?
- 4011OSHA uses the term competent person. What is it?
- 4012Under OSHA rules, how must safety training be provided to workers?
- 4013A foreman notices a technician using a ladder with a cracked rail. What is the supervisor's duty?
- 4014A technician must enter a tank room that is a permit-required confined space. What should the supervisor do?
- 4015Under the NICET Code of Ethics, what should a certified technician do if asked to sign off on a test that was not performed?
- 4016Under the NICET Code of Ethics, what may a certified technician do regarding work outside their certified area?
- 4017Under the NICET Code of Ethics, what should a technician do when they learn that an installation endangers public safety and the employer refuses to correct it?
- 4018How should a NICET certified technician use their certification in advertising?
- 4019Under AIA A201, who is solely responsible for construction means, methods, techniques, sequences, and procedures?
- 4020Under AIA A201, are shop drawings part of the Contract Documents?
- 4021Under AIA A201, what must the Contractor do before sending shop drawings to the Architect?
- 4022Under AIA A201, what is a Change Order?
- 4023Under AIA A201, what is a Construction Change Directive?
- 4024Under AIA A201, the Architect orders a minor change in the work that does not affect cost or time. What is this called?
- 4025Under AIA A201, how long after Substantial Completion must the Contractor generally correct work found not to conform?
- 4026Under AIA A201, how soon must a Claim be made after the claimant first recognizes the condition giving rise to it?
- 4027Under AIA A201, what should the Contractor do on discovering an error between the drawings and specifications?
- 4028Under AIA A201, what does Substantial Completion mean?
- 4029A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?
- 4030A project manager prepares a bid for a fire alarm installation. Which item is most essential to include from the specification?
- 4031Which estimate component covers costs like insurance, office rent, and accounting that are not tied to a single job?
- 4032On a construction contract, what is retainage?
- 4033What does a payment bond protect?
- 4034What does a performance bond guarantee?
- 4035A Level III supervises a Level I technician installing devices. Which supervision practice best ensures quality?
- 4036A technician repeatedly fails to follow lockout procedures. What should the supervisor do?
- 4037Which document should be created at the end of each workday on a large fire alarm project?
- 4038A schedule shows fire alarm acceptance testing three days before the certificate of occupancy date. What is the main risk?
- 4039Which approach helps a project manager control material costs on a fire alarm job?
- 4040A manufacturer releases a firmware update for the control unit after installation. How should the project manager handle it?
- 4041A worker is exposed to noise of 95 dBA during testing of horns. What should the supervisor ensure?
- 4042A project has 4,800 labor hours estimated for installation. After 60 percent of the work is complete, 3,300 hours have been used. If the trend continues, about how many total hours will the job take?
- 4043A fire alarm job has a contract value of $240,000. Direct costs are $180,000 and allocated overhead is $36,000. What is the net profit as a percentage of the contract value?
- 4044The owner's representative asks your technician on site to add four strobes in a new room. What should the Level III project manager require before the work proceeds?
- 4045A subcontract requires the fire alarm contractor to carry insurance naming the general contractor as additional insured. What should the project manager provide before starting work?