Question 4012 of 243 · NICET Fire Alarm Systems Level IV

In a building with smoke control, which panel has the highest priority over the smoke control equipment?

Exactly one answer is correct.

Show solution

Correct answer to question 4012

  • C: The firefighter's smoke control panel

Explanation

The IBC requires the firefighter's smoke control panel to have the highest priority over all other control sources for smoke control fans and dampers. Fire service commands must not be overridden by other systems.