Who usually performs the required acceptance inspection of a smoke control system under the IBC?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4019
- A: A qualified special inspector
Explanation
IBC requires special inspection of smoke control systems by an approved, qualified agency. The special inspector verifies installation, leakage and operating modes before approval.
More questions: Complex Detection, Integrated and Special Systems
- 4020What is a releasing service fire alarm control unit used for?
- 4021A clean agent system design calls for an abort switch. Where should it be located?
- 4022Which abort switch operation is generally recommended for clean agent systems?
- 4023What must happen when a releasing system disconnect switch is placed in the disconnect position?
- 4024A double interlock preaction system is being designed. What two events are needed to fill the piping with water?
- 4025Why is cross-zoning or counting zones used for clean agent release?