Question 4054 of 243 · NICET Fire Alarm Systems Level IV
An owner asks whether a new office tower needs an ERCES. What is the right first step?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4054
- C: Measure existing public safety signal levels against the required coverage
Explanation
ERCES is needed where the building does not provide the required public safety radio coverage. A signal survey after enough of the shell is built shows where coverage falls short and drives the design.
More questions: Complex Detection, Integrated and Special Systems
- 4055How often must an ERCES be tested after acceptance under the IFC?
- 4056A fire alarm department starts a training program for new technicians. Which approach best follows adult learning principles?
- 4057How should a fire alarm company demonstrate that its technicians are qualified?
- 4058A Level IV technician wants to influence future editions of NFPA 72. What is the formal route?
- 4059A project is planned in a new jurisdiction. What step best builds a good working relationship with the AHJ?
- 4060What OSHA requirement applies when technicians may be exposed to energized circuits during testing?