Question 4054 of 243 · NICET Fire Alarm Systems Level IV

An owner asks whether a new office tower needs an ERCES. What is the right first step?

Exactly one answer is correct.

Show solution

Correct answer to question 4054

  • C: Measure existing public safety signal levels against the required coverage

Explanation

ERCES is needed where the building does not provide the required public safety radio coverage. A signal survey after enough of the shell is built shows where coverage falls short and drives the design.