Question 6006 of 153 · Oklahoma Fire Alarm Technician Exam
Before working on the 120 V branch circuit that feeds a fire alarm control unit, what should the technician do?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 6006
- C: Deenergize it, apply lockout and tagout, and verify it is dead with a tester
Explanation
The primary supply is line voltage. Safe practice and OSHA require deenergizing, locking and tagging the disconnect, and testing for absence of voltage before work.
More questions: Job Site Safety
- 6007A technician must enter a tank vault classified as a permit required confined space to service a device. What is required?
- 6008Eye protection used while drilling overhead for device mounting should meet which standard?
- 6009On a construction site, what protection does OSHA require for 120 V, 15 and 20 A temporary receptacles used by workers?
- 6010Head protection worn on a construction site must meet which standard?
- 6011Above what 8 hour time weighted average noise level must OSHA's construction noise controls or hearing protection be used?
- 6012At what height does a scaffold platform require fall protection such as guardrails?