Question 1055 of 172 · Texas Fire Alarm License Exam
If corrective action from an installation inspection is not started within ten calendar days, the registered firm must
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1055
- C: notify the authority having jurisdiction
Explanation
The registered firm must notify the AHJ if corrective action does not begin within ten calendar days. The inspection form is kept at the firm's office for five years.
More questions: Texas Fire Alarm Law and Rules
- 1056The installation label for a new fire alarm system must be
- 1057Which label must NOT be attached for the installation of a new system?
- 1058Which signature is NOT acceptable on Texas fire alarm labels?
- 1059After any service on a fire alarm system, the licensee must attach a
- 1060Service labels must remain in place for at least
- 1061What color is the Texas inspection/test label?