Question 4042 of 297 · NICET Fire Alarm Systems Level III
A project has 4,800 labor hours estimated for installation. After 60 percent of the work is complete, 3,300 hours have been used. If the trend continues, about how many total hours will the job take?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4042
- B: About 5,500 hours
Explanation
Earned hours at 60 percent: 0.60 x 4,800 = 2,880. Actual is 3,300, so productivity is 2,880 / 3,300 = 0.873. Forecast total: 4,800 / 0.873 = about 5,500 hours, or 3,300 / 0.60 = 5,500. The job is trending about 700 hours over.
More questions: Management and Supervision
- 4043A fire alarm job has a contract value of $240,000. Direct costs are $180,000 and allocated overhead is $36,000. What is the net profit as a percentage of the contract value?
- 4044The owner's representative asks your technician on site to add four strobes in a new room. What should the Level III project manager require before the work proceeds?
- 4045A subcontract requires the fire alarm contractor to carry insurance naming the general contractor as additional insured. What should the project manager provide before starting work?
- 4001Under OSHA construction rules, at what height must workers on a walking-working surface with an unprotected edge generally be protected from falls?
- 4002A technician uses a portable extension ladder to reach a roof edge. How far must the side rails extend above the upper landing?
- 4003A non-self-supporting ladder is 20 ft long to the support point. About how far from the wall should its base be?