A project has 4,800 labor hours estimated for installation. After 60 percent of the work is complete, 3,300 hours have been used. If the trend continues, about how many total hours will the job take?

Exactly one answer is correct.

Show solution

Correct answer to question 4042

  • B: About 5,500 hours

Explanation

Earned hours at 60 percent: 0.60 x 4,800 = 2,880. Actual is 3,300, so productivity is 2,880 / 3,300 = 0.873. Forecast total: 4,800 / 0.873 = about 5,500 hours, or 3,300 / 0.60 = 5,500. The job is trending about 700 hours over.