A company is invited to bid a design build fire alarm upgrade. What is the most important step before preparing the price?

Exactly one answer is correct.

Show solution

Correct answer to question 1070

  • A: A site survey to verify existing conditions, access and pathways

Explanation

Existing conditions drive cost on retrofits. A site survey reveals hard ceilings, asbestos, occupied areas and reusable pathways that a desk estimate would miss. Bidding without it shifts risk onto the contractor.