Question 1071 of 243 · NICET Fire Alarm Systems Level IV
In a proposal for a retrofit, why should the contractor list clarifications and exclusions?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1071
- C: To define the scope and show what is excluded, such as patching or permit fees
Explanation
Clear exclusions prevent scope gaps and disputes. If patching, painting, conduit or fees are not listed as excluded, the owner may assume they are included. Exclusions cannot remove the contractor's duty to install a code compliant system.
More questions: Installation, Planning and Maintenance Management
- 1072Which federal law requires contractors on federally funded construction contracts over 2,000 dollars to pay locally prevailing wages?
- 1073Which federal law requires performance and payment bonds on federal construction contracts above the set threshold?
- 1074How long must an employer keep the OSHA Form 300 injury and illness log?
- 1075During which period must the OSHA Form 300A annual summary be posted in the workplace?
- 1076A technician is hospitalized as an inpatient after a fall on a job site. Within what time must the employer report this to OSHA?
- 1077A former employee left the company 18 months ago after working there for 4 years. Until when must the company keep that person's Form I-9?