Question 2016 of 243 · NICET Fire Alarm Systems Level IV

How long must the record of completion and the record drawings be retained?

Exactly one answer is correct.

Show solution

Correct answer to question 2016

  • B: For the life of the system

Explanation

Completion documentation and record drawings describe the installed system and are retained for the life of the system. Test records have a shorter retention tied to the next test.