Question 2022 of 243 · NICET Fire Alarm Systems Level IV
When a performance-based design is used for detection in an atrium, what documentation must be provided?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2022
- A: The objectives, design fires, assumptions and analysis, approved by the AHJ
Explanation
A performance-based design must document the goals and objectives, the design fires, the assumptions and the analysis that shows the objectives are met, and it needs AHJ approval. These assumptions must be maintained over the building's life.
More questions: Submittals, Shop Drawings and Records
- 2023Why must the assumptions of a performance-based detection design be recorded and kept with the system documents?
- 2024For an emergency communication system, what must happen to the risk analysis?
- 2025Which design documents must state the pathway survivability level used for each circuit of a voice evacuation system?
- 2026A voice system design treats storage closets as not requiring intelligible voice. Where must this decision be documented?
- 2031Which item should an ITM inspection and test record include?
- 2032A technician finds that 14 smoke detectors failed sensitivity testing. How should this be documented?