Question 2022 of 243 · NICET Fire Alarm Systems Level IV

When a performance-based design is used for detection in an atrium, what documentation must be provided?

Exactly one answer is correct.

Show solution

Correct answer to question 2022

  • A: The objectives, design fires, assumptions and analysis, approved by the AHJ

Explanation

A performance-based design must document the goals and objectives, the design fires, the assumptions and the analysis that shows the objectives are met, and it needs AHJ approval. These assumptions must be maintained over the building's life.

Next to question ›