Question 4033 of 153 · Oklahoma Fire Alarm Technician Exam

Where must splices in fire alarm conductors be made?

Exactly one answer is correct.

Show solution

Correct answer to question 4033

  • A: In a box, enclosure or listed fitting

Explanation

Splices and terminations are made in boxes, enclosures or listed fittings. Splices inside raceways or loose above ceilings are not permitted.

Next to question ›