Before touching conductors you have de-energized, you test them with a voltage tester. What else must you do?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1117
- B: Check the tester on a known live source before and after the test
Explanation
OSHA requires the test instrument to be checked for proper operation immediately before and after the test, so a dead meter cannot give a false no-voltage reading.
More questions: Installation (Peripherals, Cabling, Job Site Safety)
- 1118You need to replace a power supply board inside a fire alarm control unit. What must be disconnected to make the unit safe?
- 1119On a construction site, which receptacles used by employees require ground-fault circuit interrupter protection?
- 1120You are drilling overhead into a concrete ceiling to mount a device box. What eye protection is required?
- 1121Drilling into concrete creates dust that contains respirable crystalline silica. Which control method is typical under the OSHA silica standard?
- 1122While pulling cable above a ceiling, you find old sprayed-on fireproofing that may contain asbestos. What should you do?
- 1123Where can a worker find the hazards, PPE and first aid measures for a chemical such as firestop sealant?