During an initial acceptance test, which devices must be tested?

Exactly one answer is correct.

Show solution

Correct answer to question 1083

  • A: Every device, appliance, and function

Explanation

Initial acceptance testing covers 100 percent of the system, including every initiating device, notification appliance, control function, and interface, following the test methods of Chapter 14.