Question 1082 of 344 · NICET Fire Alarm Systems Level II

What is the purpose of system commissioning before the acceptance test?

Exactly one answer is correct.

Show solution

Correct answer to question 1082

  • B: To prove the system works before the AHJ witness test

Explanation

Commissioning, often called a 100 percent pretest, verifies wiring, addresses, programming, and every input and output against the sequence of operations. The AHJ acceptance test then confirms a system already known to work.

Next to question ›