What is the purpose of system commissioning before the acceptance test?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1082
- B: To prove the system works before the AHJ witness test
Explanation
Commissioning, often called a 100 percent pretest, verifies wiring, addresses, programming, and every input and output against the sequence of operations. The AHJ acceptance test then confirms a system already known to work.
More questions: Installation
- 1083During an initial acceptance test, which devices must be tested?
- 1084Before connecting field wiring to the control unit, which test checks for unintended grounds and stray voltage on new circuits?
- 1085What instrument is used to measure insulation resistance of new fire alarm conductors to ground?
- 1086Where must spot smoke detectors be installed relative to a ceiling fan blade?
- 1087A smoke detector is planned in a room where the ambient temperature can reach 120 F. What must the technician verify?
- 1088Why should smoke detectors generally not be installed until construction cleanup is complete?