Before connecting field wiring to the control unit, which test checks for unintended grounds and stray voltage on new circuits?

Exactly one answer is correct.

Show solution

Correct answer to question 1084

  • B: Insulation and stray voltage checks

Explanation

New wiring is checked for stray voltage, ground faults, short circuits, and correct loop resistance before it is connected. This prevents damage to the control unit and finds installation faults early.