Question 2016 of 344 · NICET Fire Alarm Systems Level II
After testing is complete, what must the technician do with persons notified before the test?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2016
- B: Tell them testing is done and the system is restored
Explanation
At the end of testing, the same parties notified before the test must be told that testing is finished and the system is restored to normal.
More questions: Maintenance
- 2017Who is responsible for the inspection, testing, and maintenance of a fire alarm system?
- 2019Which visual inspection frequency applies to waterflow and supervisory devices under NFPA 72 (2022)?
- 2020How often should the fire alarm control unit receive a visual inspection when the system is monitored for alarm, supervisory, and trouble signals?
- 2021How often must a control unit that is NOT monitored for alarm, supervisory, and trouble signals be visually inspected?
- 2022What is the purpose of a visual inspection before a functional test of devices?
- 2023A new wall was built in an open office, splitting a room so one part has no smoke detector. Which inspection step should catch this?