Question 3071 of 344 · NICET Fire Alarm Systems Level II

When should fire alarm shop drawings normally be approved by the AHJ?

Exactly one answer is correct.

Show solution

Correct answer to question 3071

  • B: Before installation work starts

Explanation

Most AHJs require plan approval before a permit is issued and installation begins. Working from approved drawings avoids costly rework found during inspection.