Question 4034 of 344 · NICET Fire Alarm Systems Level II
Which record helps a supervisor prove what work was done on a given day on site?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4034
- B: A daily job log with work completed, crew, and issues
Explanation
Daily logs record work completed, workers on site, delays, inspections, and instructions received. They support progress billing and help resolve claims later.
More questions: Management and Supervision
- 4035A crew must braze a pipe support near an area with active smoke detectors. Which step should the supervisor arrange first?
- 4001When a portable ladder is used to reach an upper landing, how far must its side rails extend above the landing?
- 4002A non self supporting ladder is 16 ft long from base to support point. How far should the base be from the wall?
- 4003In construction, at what height above a lower level must workers on unprotected sides and edges have fall protection?
- 4004At what height do workers on a scaffold need fall protection under OSHA construction rules?
- 4005A technician must service a 120 V circuit feeding a fire alarm booster power supply. Under OSHA lockout/tagout rules, who may remove the lock afterward?