Question 4035 of 344 · NICET Fire Alarm Systems Level II

A crew must braze a pipe support near an area with active smoke detectors. Which step should the supervisor arrange first?

Exactly one answer is correct.

Show solution

Correct answer to question 4035

  • A: A hot work permit with fire watch, and a planned detector bypass

Explanation

Hot work needs a permit, combustibles cleared or protected, and a fire watch. Any detector disabling must be planned as an impairment with notifications and restored as soon as the work ends.