Question 4035 of 344 · NICET Fire Alarm Systems Level II
A crew must braze a pipe support near an area with active smoke detectors. Which step should the supervisor arrange first?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4035
- A: A hot work permit with fire watch, and a planned detector bypass
Explanation
Hot work needs a permit, combustibles cleared or protected, and a fire watch. Any detector disabling must be planned as an impairment with notifications and restored as soon as the work ends.
More questions: Management and Supervision
- 4001When a portable ladder is used to reach an upper landing, how far must its side rails extend above the landing?
- 4002A non self supporting ladder is 16 ft long from base to support point. How far should the base be from the wall?
- 4003In construction, at what height above a lower level must workers on unprotected sides and edges have fall protection?
- 4004At what height do workers on a scaffold need fall protection under OSHA construction rules?
- 4005A technician must service a 120 V circuit feeding a fire alarm booster power supply. Under OSHA lockout/tagout rules, who may remove the lock afterward?
- 4006Which receptacles on a construction site need ground fault protection under OSHA when an assured equipment grounding program is not used?