Which item is required in the documentation for a system using a performance-based detection design?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 3054
- A: Objectives, assumptions, and the supporting analysis
Explanation
Performance-based designs must document goals, objectives, fire scenarios, assumptions, and the engineering analysis, so the AHJ can review them. The documentation must be kept with the system records.
More questions: Submittal Preparation and System Layout
- 3055What is the main purpose of the record drawings (as-built drawings) for a fire alarm system?
- 3056An engineer of record returns your shop drawings marked 'Revise and Resubmit'. What should you do?
- 3057During review, you find that the architect's reflected ceiling plan has changed, moving lights to where you placed smoke detectors. What should the Level III do?
- 3058A large open office has ceiling-mounted supply diffusers. How far must spot smoke detectors be from them?
- 3059Which ceiling height condition generally points toward projected beam or air sampling detection rather than spot smoke detectors?
- 3060What does stratification mean for smoke detector design?