A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?

Exactly one answer is correct.

Show solution

Correct answer to question 4029

  • D: Notify the GC in writing and update the schedule

Explanation

Written notice of delays caused by others protects schedule and cost rights, which A201 requires for time extension claims. It also lets the GC coordinate trades.