A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4029
- D: Notify the GC in writing and update the schedule
Explanation
Written notice of delays caused by others protects schedule and cost rights, which A201 requires for time extension claims. It also lets the GC coordinate trades.
More questions: Management and Supervision
- 4030A project manager prepares a bid for a fire alarm installation. Which item is most essential to include from the specification?
- 4031Which estimate component covers costs like insurance, office rent, and accounting that are not tied to a single job?
- 4032On a construction contract, what is retainage?
- 4033What does a payment bond protect?
- 4034What does a performance bond guarantee?
- 4035A Level III supervises a Level I technician installing devices. Which supervision practice best ensures quality?