On a construction contract, what is retainage?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4032
- B: Part of each payment, held back until completion
Explanation
Retainage is a percentage of each progress payment withheld by the owner or GC until the work is complete, to ensure the contractor finishes properly. It is often released at substantial or final completion.
More questions: Management and Supervision
- 4033What does a payment bond protect?
- 4034What does a performance bond guarantee?
- 4035A Level III supervises a Level I technician installing devices. Which supervision practice best ensures quality?
- 4036A technician repeatedly fails to follow lockout procedures. What should the supervisor do?
- 4037Which document should be created at the end of each workday on a large fire alarm project?
- 4038A schedule shows fire alarm acceptance testing three days before the certificate of occupancy date. What is the main risk?