Question 4028 of 297 · NICET Fire Alarm Systems Level III
Under AIA A201, what does Substantial Completion mean?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4028
- A: The Owner can occupy or use the work for its intended use
Explanation
A201 9.8.1 defines Substantial Completion as the stage when the work is sufficiently complete per the Contract Documents so that the Owner can occupy or use it for its intended use. Fire alarm acceptance is often a prerequisite for occupancy.
More questions: Management and Supervision
- 4029A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?
- 4030A project manager prepares a bid for a fire alarm installation. Which item is most essential to include from the specification?
- 4031Which estimate component covers costs like insurance, office rent, and accounting that are not tied to a single job?
- 4032On a construction contract, what is retainage?
- 4033What does a payment bond protect?
- 4034What does a performance bond guarantee?