Question 4037 of 297 · NICET Fire Alarm Systems Level III
Which document should be created at the end of each workday on a large fire alarm project?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4037
- B: A daily report of work, crew, and issues
Explanation
Daily reports document progress, labor, deliveries, delays, and safety events. They support schedule updates, claims, and payment applications.
More questions: Management and Supervision
- 4038A schedule shows fire alarm acceptance testing three days before the certificate of occupancy date. What is the main risk?
- 4039Which approach helps a project manager control material costs on a fire alarm job?
- 4040A manufacturer releases a firmware update for the control unit after installation. How should the project manager handle it?
- 4041A worker is exposed to noise of 95 dBA during testing of horns. What should the supervisor ensure?
- 4042A project has 4,800 labor hours estimated for installation. After 60 percent of the work is complete, 3,300 hours have been used. If the trend continues, about how many total hours will the job take?
- 4043A fire alarm job has a contract value of $240,000. Direct costs are $180,000 and allocated overhead is $36,000. What is the net profit as a percentage of the contract value?