Question 4038 of 297 · NICET Fire Alarm Systems Level III

A schedule shows fire alarm acceptance testing three days before the certificate of occupancy date. What is the main risk?

Exactly one answer is correct.

Show solution

Correct answer to question 4038

  • C: No time to fix deficiencies

Explanation

Acceptance tests often reveal deficiencies that need repair and retest, plus interface tests with elevators, HVAC, and sprinklers. A tight window risks delaying the certificate of occupancy.

Next to question ›