In a critical path schedule for a high-rise fire alarm installation, what characterizes the critical path?

Exactly one answer is correct.

Show solution

Correct answer to question 1021

  • A: The longest sequence of dependent activities, which has zero total float

Explanation

The critical path is the longest chain of dependent activities through the network and sets the earliest finish date. Activities on it have no float, so any delay to them delays the project unless recovered elsewhere.