Question 1021 of 243 · NICET Fire Alarm Systems Level IV
In a critical path schedule for a high-rise fire alarm installation, what characterizes the critical path?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1021
- A: The longest sequence of dependent activities, which has zero total float
Explanation
The critical path is the longest chain of dependent activities through the network and sets the earliest finish date. Activities on it have no float, so any delay to them delays the project unless recovered elsewhere.
More questions: Installation, Planning and Maintenance Management
- 1022An activity in your project schedule has an early start of day 12 and a late start of day 19. How much total float does it have?
- 1023Your estimated direct cost for a voice evacuation retrofit is 84,000 dollars. Company policy requires a 30 percent gross margin on the selling price. What selling price meets that policy?
- 1024A sales estimator applies a 25 percent markup to a job cost of 60,000 dollars. What gross margin results on the selling price?
- 1025A takeoff shows 480 addressable devices, each estimated at 0.75 labor hours including wiring terminations. With a crew of 3 technicians working 8 hour days, about how many working days will device installation take?
- 1026Last year your fire alarm company had 450,000 dollars of indirect overhead and 1,800,000 dollars of direct labor cost. If overhead is applied as a percentage of direct labor, what rate should the estimators use?
- 1027A service department has annual fixed costs of 360,000 dollars and earns a contribution margin of 40 percent on each dollar of revenue. What annual revenue is needed to break even?