An activity in your project schedule has an early start of day 12 and a late start of day 19. How much total float does it have?

Exactly one answer is correct.

Show solution

Correct answer to question 1022

  • A: 7 days

Explanation

Total float equals late start minus early start (or late finish minus early finish): 19 minus 12 equals 7 days. The activity can slip up to 7 days without delaying project completion.