A takeoff shows 480 addressable devices, each estimated at 0.75 labor hours including wiring terminations. With a crew of 3 technicians working 8 hour days, about how many working days will device installation take?

Exactly one answer is correct.

Show solution

Correct answer to question 1025

  • B: 15 days

Explanation

Total labor is 480 times 0.75, or 360 hours. The crew delivers 3 times 8, or 24 hours per day, so 360 divided by 24 equals 15 working days. The estimate should still add time for mobilization, testing and punch list work.