Question 1025 of 243 · NICET Fire Alarm Systems Level IV
A takeoff shows 480 addressable devices, each estimated at 0.75 labor hours including wiring terminations. With a crew of 3 technicians working 8 hour days, about how many working days will device installation take?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1025
- B: 15 days
Explanation
Total labor is 480 times 0.75, or 360 hours. The crew delivers 3 times 8, or 24 hours per day, so 360 divided by 24 equals 15 working days. The estimate should still add time for mobilization, testing and punch list work.
More questions: Installation, Planning and Maintenance Management
- 1026Last year your fire alarm company had 450,000 dollars of indirect overhead and 1,800,000 dollars of direct labor cost. If overhead is applied as a percentage of direct labor, what rate should the estimators use?
- 1027A service department has annual fixed costs of 360,000 dollars and earns a contribution margin of 40 percent on each dollar of revenue. What annual revenue is needed to break even?
- 1028Your service department must perform 1,600 annual inspections averaging 6 labor hours each. Each technician delivers about 1,400 billable hours per year. How many technicians are needed for this inspection workload alone?
- 1029On a percentage of completion job, you have billed 60 percent of the contract value while costs incurred represent 48 percent of the estimated total cost. How is the job reported on the work in progress schedule?
- 1030The owner asks your field crew to add 14 speakers in a new conference wing that is not in the contract scope. What should the project manager do before the crew starts the extra work?
- 1031A supplier who furnished control units for a private office building has not been paid. Which legal remedy lets the supplier place a claim against the improved property itself?