Question 1083 of 243 · NICET Fire Alarm Systems Level IV

A multi year retrofit contract will buy most devices more than a year after bid. Which contract provision protects the contractor from large material price increases?

Exactly one answer is correct.

Show solution

Correct answer to question 1083

  • B: A material price escalation clause

Explanation

An escalation clause lets the price adjust when defined material costs rise beyond a threshold. Without it, the lump sum price absorbs the increase. Liquidated damages and no damages for delay clauses shift risk toward the contractor instead.

Next to question ›