Question 1083 of 243 · NICET Fire Alarm Systems Level IV
A multi year retrofit contract will buy most devices more than a year after bid. Which contract provision protects the contractor from large material price increases?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1083
- B: A material price escalation clause
Explanation
An escalation clause lets the price adjust when defined material costs rise beyond a threshold. Without it, the lump sum price absorbs the increase. Liquidated damages and no damages for delay clauses shift risk toward the contractor instead.
More questions: Installation, Planning and Maintenance Management
- 1084A department manager reports a backlog of 2.4 million dollars. What does backlog mean?
- 1085A fire alarm system is returned to service after a 2 day impairment for a control unit repair. What should happen before the impairment is closed out?
- 1086A failed smoke detector is replaced with an identical model at the same address. What test is required?
- 1087At the end of a project, what is the usual purpose of the AHJ's acceptance test?
- 1088Which role is most important for a Level IV technician acting as liaison on a multi stakeholder project?
- 1089A building owner wants proof each year that the fire alarm ITM program is being followed. Which deliverable best provides this?