Question 1087 of 243 · NICET Fire Alarm Systems Level IV
At the end of a project, what is the usual purpose of the AHJ's acceptance test?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1087
- D: To witness that the completed system works as approved and meets code
Explanation
The AHJ witnesses the contractor's demonstration of a fully pretested system and checks it against approved plans and the code. The contractor remains responsible for the installation and its testing.
More questions: Installation, Planning and Maintenance Management
- 1088Which role is most important for a Level IV technician acting as liaison on a multi stakeholder project?
- 1089A building owner wants proof each year that the fire alarm ITM program is being followed. Which deliverable best provides this?
- 1090When an operations manager plans staff for a campus ITM contract, why should deficiency repairs be estimated separately from routine testing?
- 1091Which factor makes a cost plus contract riskier for the owner than a lump sum contract?
- 1092A project's planned labor for rough in was 900 hours for 60 percent of the work. Actual hours spent are 1,080 for that 60 percent. What is the labor productivity factor compared with plan?
- 1093Which IBC requirement typically applies before fire alarm work begins in a new building?