Question 1087 of 243 · NICET Fire Alarm Systems Level IV

At the end of a project, what is the usual purpose of the AHJ's acceptance test?

Exactly one answer is correct.

Show solution

Correct answer to question 1087

  • D: To witness that the completed system works as approved and meets code

Explanation

The AHJ witnesses the contractor's demonstration of a fully pretested system and checks it against approved plans and the code. The contractor remains responsible for the installation and its testing.

Next to question ›