Question 1090 of 243 · NICET Fire Alarm Systems Level IV
When an operations manager plans staff for a campus ITM contract, why should deficiency repairs be estimated separately from routine testing?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1090
- D: Repairs depend on test results and are usually priced as extra work
Explanation
Routine testing is predictable from the device inventory, while repairs depend on what fails. Pricing them separately avoids losses and keeps the owner informed through deficiency reports and quotes.
More questions: Installation, Planning and Maintenance Management
- 1091Which factor makes a cost plus contract riskier for the owner than a lump sum contract?
- 1092A project's planned labor for rough in was 900 hours for 60 percent of the work. Actual hours spent are 1,080 for that 60 percent. What is the labor productivity factor compared with plan?
- 1093Which IBC requirement typically applies before fire alarm work begins in a new building?
- 1094A new service manager wants to measure how well the department keeps customers' systems compliant. Which indicator is most directly related?
- 1095A designer is asked to estimate total amplifier wattage for budgeting a voice system with 220 speakers tapped at 1 watt and 40 speakers tapped at 2 watts. The spec requires 25 percent spare capacity. What minimum amplifier capacity should be budgeted?
- 1096A project manager compares a bid from a subcontractor that is 30 percent below the other bids. What is the most prudent response?