Question 1092 of 243 · NICET Fire Alarm Systems Level IV
A project's planned labor for rough in was 900 hours for 60 percent of the work. Actual hours spent are 1,080 for that 60 percent. What is the labor productivity factor compared with plan?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1092
- D: 0.83, meaning the crew is less productive than planned
Explanation
Productivity equals planned hours divided by actual hours for the same work: 900 divided by 1,080 equals 0.83. A factor below 1 means more hours are used than planned, which warrants a look at crew size, access or scope changes.
More questions: Installation, Planning and Maintenance Management
- 1093Which IBC requirement typically applies before fire alarm work begins in a new building?
- 1094A new service manager wants to measure how well the department keeps customers' systems compliant. Which indicator is most directly related?
- 1095A designer is asked to estimate total amplifier wattage for budgeting a voice system with 220 speakers tapped at 1 watt and 40 speakers tapped at 2 watts. The spec requires 25 percent spare capacity. What minimum amplifier capacity should be budgeted?
- 1096A project manager compares a bid from a subcontractor that is 30 percent below the other bids. What is the most prudent response?
- 1097Which statement about the relationship between the fire alarm contractor and the engineer of record is typically true on a design bid build project?
- 1098A project includes work in an occupied hospital. Which item should be part of the project plan before work begins?