Question 1092 of 243 · NICET Fire Alarm Systems Level IV

A project's planned labor for rough in was 900 hours for 60 percent of the work. Actual hours spent are 1,080 for that 60 percent. What is the labor productivity factor compared with plan?

Exactly one answer is correct.

Show solution

Correct answer to question 1092

  • D: 0.83, meaning the crew is less productive than planned

Explanation

Productivity equals planned hours divided by actual hours for the same work: 900 divided by 1,080 equals 0.83. A factor below 1 means more hours are used than planned, which warrants a look at crew size, access or scope changes.

Next to question ›