Question 1096 of 243 · NICET Fire Alarm Systems Level IV

A project manager compares a bid from a subcontractor that is 30 percent below the other bids. What is the most prudent response?

Exactly one answer is correct.

Show solution

Correct answer to question 1096

  • C: Review scope, quantities and assumptions with the bidder before awarding

Explanation

A bid far below others often signals a missed scope item or an error. Confirming scope protects the project from a subcontractor who cannot complete at that price. Rejecting a bid without review is also not good practice.