Question 4030 of 243 · NICET Fire Alarm Systems Level IV

An elevator hoistway has sprinklers. Where must heat detectors for shunt trip be located?

Exactly one answer is correct.

Show solution

Correct answer to question 4030

  • C: Within 2 ft of each sprinkler

Explanation

Heat detectors used for elevator power shutdown must be within 24 in. of each sprinkler in the hoistway or machine room. They must have a lower temperature rating and higher sensitivity than the sprinklers so power is removed first.