Question 6015 of 183 · Ohio Fire Alarm Certification Exam
How many devices must be tested during the initial acceptance test of a new fire alarm system?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 6015
- A: All of them
Explanation
NFPA 72 requires a 100 percent acceptance test of all devices, appliances and functions of a new system, witnessed by the AHJ where required.
More questions: Inspection, Testing and Maintenance
- 6016Why is a magnet test alone not enough for a functional test of a smoke detector?
- 6017What must be verified when testing a duct smoke detector with sampling tubes?
- 6018Which item must an NFPA 72 inspection and test report include?
- 6019A defect found during inspection is not corrected by the end of the visit. What should the technician do?
- 6020How often must a household fire alarm system with a control unit be tested by a qualified technician?
- 6021A smoke detector's measured sensitivity is outside its listed range. What must be done?