Question 2054 of 299 · NICET Fire Alarm Systems Level I
To test the transfer to secondary power, the technician switches off the AC branch circuit. What should happen?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2054
- D: The system keeps working on batteries and shows an AC power trouble
Explanation
Loss of primary power must transfer the system to the secondary supply without losing signals, and the panel must show a trouble for the AC loss. Restore AC after the test and confirm the trouble clears.
More questions: Maintenance (Periodic Testing, Repair and Replacement)
- 2055On a control unit, what is the difference between silencing and resetting?
- 2056What signal type does a fire alarm panel use to report a fault in the system, such as an open circuit?
- 2057A sprinkler control valve has been closed. What type of signal should the panel show?
- 2058During an inspection you see the panel's trouble LED lit and the buzzer was silenced last week. What should you do?
- 2059How often is a visual inspection of control equipment required on a system that is monitored for alarm, supervisory and trouble signals by a supervising station?
- 2060During a visual inspection of smoke detectors, what are you mainly looking for?