Question 2048 of 344 · NICET Fire Alarm Systems Level II
After repairing a deficiency, what testing must be done?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2048
- D: Test the repaired part and every affected function
Explanation
Reacceptance testing after a repair or replacement covers the components and functions affected. For example, a replaced detector is tested, and the panel response and outputs for it are confirmed.
More questions: Maintenance
- 2049After a change to site specific software, how many initiating devices not directly affected by the change must be tested?
- 2050A software change affects 3 devices. The system has 380 initiating devices total. How many unaffected devices must also be tested?
- 2051A site specific software change is made on a system with 1200 initiating devices. What is the maximum number of unaffected devices required to be tested?
- 2052When the control unit firmware (executive software) is changed, what must be done?
- 2053How long must records of inspection, testing, and maintenance be retained?
- 2054How long must the original acceptance test records be retained?