Question 2048 of 344 · NICET Fire Alarm Systems Level II

After repairing a deficiency, what testing must be done?

Exactly one answer is correct.

Show solution

Correct answer to question 2048

  • D: Test the repaired part and every affected function

Explanation

Reacceptance testing after a repair or replacement covers the components and functions affected. For example, a replaced detector is tested, and the panel response and outputs for it are confirmed.

Next to question ›