Question 2104 of 344 · NICET Fire Alarm Systems Level II
After an inspection, the service company finds deficiencies it cannot fix that day. What must the report include?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 2104
- D: The deficiencies and that the owner was told
Explanation
Inspection and test records must list deficiencies and corrective actions needed, and the owner must be notified in writing. This gives the owner the information to arrange repairs or impairment measures.
More questions: Maintenance
- 2105A technician measures 4.2 kilohms across a Class B IDC at the panel with field wiring disconnected. The EOL is 4.7 kilohms. What is the most likely issue?
- 2001How often must the sensitivity of system smoke detectors be checked after the first check?
- 2002When must the first sensitivity check of a newly installed smoke detector be done?
- 2003Which of these methods is NOT an acceptable way to check smoke detector sensitivity?
- 2004A smoke detector's sensitivity is found outside its listed and marked range. What must be done?
- 2005How often are restorable spot heat detectors functionally tested?