Which documents must be provided to the owner at the completion of a new system?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 3080
- B: Owner's manual, record drawings, and the record of completion
Explanation
The owner receives the owner's manual and installation instructions, record drawings, the completed record of completion, and site specific software. These are kept in the documentation cabinet.
More questions: Submittal Preparation and System Layout
- 3081A system uses a digital alarm communicator transmitter (DACT). What does NFPA 72 require for its transmission means?
- 3082Under the IBC, where is a two way communication system generally required for accessible means of egress in a multistory building?
- 3083What must be stated on a shop drawing title block?
- 3084Which item should a designer include so the AHJ can see how the system responds to a waterflow signal on floor 3?
- 3085A building has a 30 ft wide by 120 ft long room with a smooth 12 ft ceiling. Spot smoke detectors use S = 30 ft. How many are needed in a single row down the center?
- 3086On a shop drawing, what does the symbol legend do?