Question 4027 of 344 · NICET Fire Alarm Systems Level II
On a project schedule, what is the critical path?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4027
- C: The longest chain of dependent tasks that sets the finish date
Explanation
The critical path is the sequence of dependent activities with no float. A delay on any of them delays the project finish unless other work is accelerated.
More questions: Management and Supervision
- 4028A wire takeoff from the drawings measures 2,400 ft of cable. The supervisor adds 10 percent for waste and routing. How much cable should be ordered?
- 4029A project has 120 devices. Each takes about 0.75 labor hours to install and terminate. With a crew of two technicians, how many working hours will it take?
- 4030Why should fire alarm devices and equipment be ordered only after the submittals are approved?
- 4031Which qualification does NFPA 72 accept for personnel who perform inspection, testing, and maintenance?
- 4032At the start of each work day on a fire alarm job, which supervisor action best supports safe and efficient work?
- 4033A customer asks the technician to disable a nuisance detector permanently. What should the supervisor do?