On a project schedule, what is the critical path?

Exactly one answer is correct.

Show solution

Correct answer to question 4027

  • C: The longest chain of dependent tasks that sets the finish date

Explanation

The critical path is the sequence of dependent activities with no float. A delay on any of them delays the project finish unless other work is accelerated.