Question 4029 of 344 · NICET Fire Alarm Systems Level II

A project has 120 devices. Each takes about 0.75 labor hours to install and terminate. With a crew of two technicians, how many working hours will it take?

Exactly one answer is correct.

Show solution

Correct answer to question 4029

  • D: 45 hours

Explanation

Total labor = 120 x 0.75 = 90 labor hours. Two technicians working together share this, so 90 / 2 = 45 working hours.