A project has 120 devices. Each takes about 0.75 labor hours to install and terminate. With a crew of two technicians, how many working hours will it take?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4029
- D: 45 hours
Explanation
Total labor = 120 x 0.75 = 90 labor hours. Two technicians working together share this, so 90 / 2 = 45 working hours.
More questions: Management and Supervision
- 4030Why should fire alarm devices and equipment be ordered only after the submittals are approved?
- 4031Which qualification does NFPA 72 accept for personnel who perform inspection, testing, and maintenance?
- 4032At the start of each work day on a fire alarm job, which supervisor action best supports safe and efficient work?
- 4033A customer asks the technician to disable a nuisance detector permanently. What should the supervisor do?
- 4034Which record helps a supervisor prove what work was done on a given day on site?
- 4035A crew must braze a pipe support near an area with active smoke detectors. Which step should the supervisor arrange first?