Question 2019 of 297 · NICET Fire Alarm Systems Level III

A water leak damages a notification appliance circuit at 2 a.m. and the night guard calls your service line. What is the correct order of priorities?

Exactly one answer is correct.

Show solution

Correct answer to question 2019

  • C: Confirm interim measures and notifications, repair, then retest the affected portion and restore

Explanation

An emergency impairment needs prompt notification of the owner, the supervising station, and the AHJ as required, and interim measures such as a fire watch. After repair, the restored part of the system must be tested before the impairment is closed out.

Next to question ›