Question 2072 of 297 · NICET Fire Alarm Systems Level III

A sprinkler contractor will close a control valve to repair a branch line. From the fire alarm perspective, how should this be managed?

Exactly one answer is correct.

Show solution

Correct answer to question 2072

  • B: As a planned impairment with notifications, then restore and verify the switch

Explanation

Closing a valve impairs the sprinkler system and produces a supervisory signal. It should be handled as a planned impairment with notifications and interim measures, and the valve and switch must be returned to normal and verified when the work is done.