Under AIA A201, what should the Contractor do on discovering an error between the drawings and specifications?

Exactly one answer is correct.

Show solution

Correct answer to question 4027

  • B: Report it promptly to the Architect

Explanation

A201 3.2.2 and 3.2.3 require the Contractor to report errors, inconsistencies, or omissions it discovers to the Architect as a request for information. Proceeding knowingly makes the Contractor responsible for the result.