Under AIA A201, what should the Contractor do on discovering an error between the drawings and specifications?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 4027
- B: Report it promptly to the Architect
Explanation
A201 3.2.2 and 3.2.3 require the Contractor to report errors, inconsistencies, or omissions it discovers to the Architect as a request for information. Proceeding knowingly makes the Contractor responsible for the result.
More questions: Management and Supervision
- 4028Under AIA A201, what does Substantial Completion mean?
- 4029A fire alarm subcontractor's crew will be late because a ceiling is not closed in. What is the best project management response?
- 4030A project manager prepares a bid for a fire alarm installation. Which item is most essential to include from the specification?
- 4031Which estimate component covers costs like insurance, office rent, and accounting that are not tied to a single job?
- 4032On a construction contract, what is retainage?
- 4033What does a payment bond protect?