Question 1018 of 243 · NICET Fire Alarm Systems Level IV
A contract states that the contractor will owe the owner 1,500 dollars for each calendar day the fire alarm acceptance test is late. What is this provision called?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1018
- C: Liquidated damages
Explanation
Liquidated damages are a predetermined daily amount agreed in the contract for late completion, used because actual damages are hard to prove. Project managers must track schedule float closely when such a clause applies.
More questions: Installation, Planning and Maintenance Management
- 1019Which bond protects the owner if the fire alarm contractor fails to complete the work according to the contract?
- 1020A supplier of fire alarm devices has not been paid by the electrical contractor. Which bond on a public project protects that supplier?
- 1021In a critical path schedule for a high-rise fire alarm installation, what characterizes the critical path?
- 1022An activity in your project schedule has an early start of day 12 and a late start of day 19. How much total float does it have?
- 1023Your estimated direct cost for a voice evacuation retrofit is 84,000 dollars. Company policy requires a 30 percent gross margin on the selling price. What selling price meets that policy?
- 1024A sales estimator applies a 25 percent markup to a job cost of 60,000 dollars. What gross margin results on the selling price?