A contract states that the contractor will owe the owner 1,500 dollars for each calendar day the fire alarm acceptance test is late. What is this provision called?

Exactly one answer is correct.

Show solution

Correct answer to question 1018

  • C: Liquidated damages

Explanation

Liquidated damages are a predetermined daily amount agreed in the contract for late completion, used because actual damages are hard to prove. Project managers must track schedule float closely when such a clause applies.