Question 1017 of 243 · NICET Fire Alarm Systems Level IV
The general contractor withholds 10 percent of each progress payment from the fire alarm subcontractor until the project is accepted. What is this withheld money called?
Exactly one answer is correct.
You got of questions right. Here on the question pages nobody remembers which ones you got wrong. The trainer saves your progress and asks the mistakes again until they stick.
Or free: the 10 questions most people get wrong
Show solution
Correct answer to question 1017
- B: Retainage
Explanation
Retainage is a portion of each payment held back to secure completion and correction of punch list items. It is released at substantial or final completion according to the contract. Liquidated damages are a separate charge for late completion.
More questions: Installation, Planning and Maintenance Management
- 1018A contract states that the contractor will owe the owner 1,500 dollars for each calendar day the fire alarm acceptance test is late. What is this provision called?
- 1019Which bond protects the owner if the fire alarm contractor fails to complete the work according to the contract?
- 1020A supplier of fire alarm devices has not been paid by the electrical contractor. Which bond on a public project protects that supplier?
- 1021In a critical path schedule for a high-rise fire alarm installation, what characterizes the critical path?
- 1022An activity in your project schedule has an early start of day 12 and a late start of day 19. How much total float does it have?
- 1023Your estimated direct cost for a voice evacuation retrofit is 84,000 dollars. Company policy requires a 30 percent gross margin on the selling price. What selling price meets that policy?